Wednesday 17th October

No work was done, Tuesday, on day six but resumed on day seven:

Work continued in the morning. By lunch time  a high spring tide stopped work.
In spite of the high tide nothing appeared to have been washed away.
Work continued later and more hoggin was added to the bank.